CONSTRUCTIONONGOING

Vacuum Station Odor Control Construction Reaches 70 Percent

Belle Construction is executing the $4.01 million Vacuum Stations Odor Control project, now 70% complete with new odor control systems operational at all stations. The District granted a 195-day time extension for generator procurement, with final completion scheduled for September 17, 2026.

Document date · July 21, 2026

Track Key Largo Wastewater Treatment District contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Key Largo Wastewater Treatment District.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Original Contract Amount: $4,009,141.26; Current Contract: $4,009,141.26
Contract type
CONSTRUCTION
Contract term
Contract Start Date: 03/28/2025; Substantial Completion: 08/18/2026; Final Completion: 09/17/2026
Renewal date
2026-09-17
Renewal
Project received a 195-day time extension via change order to accommodate generator delivery and installation, but the overall contract value remains at $4,009,141.26. No separate renewal terms beyond this schedule extension are described.
Document type
AgendaPacket
Source document
Key Largo Wastewater Treatment District Board of Commissioners Meeting Agenda Packet 2026-07-21

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Key Largo Wastewater Treatment District?

Belle Construction was awarded this construction contract by Key Largo Wastewater Treatment District, as recorded on July 21, 2026. The contract value is Original Contract Amount: $4,009,141.26; Current Contract: $4,009,141.26.

How much is the Belle Construction contract with Key Largo Wastewater Treatment District worth?

The Belle Construction contract with Key Largo Wastewater Treatment District is valued at Original Contract Amount: $4,009,141.26; Current Contract: $4,009,141.26, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in Key Largo Wastewater Treatment District Board of Commissioners Meeting Agenda Packet 2026-07-21 (AgendaPacket), dated July 21, 2026 from Key Largo Wastewater Treatment District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Belle Construction hold?

Belle Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Belle Construction's profile

What is Key Largo Wastewater Treatment District currently buying?

Explore Key Largo Wastewater Treatment District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Key Largo Wastewater Treatment District's profile