CONSTRUCTIONAMENDED

St. Ville Elementary construction contract amended via Change Order 011

Jefferson Parish School Board is processing Change Order 011 with Gibbs Construction, LLC for the St. Ville Elementary School project, adding $73,807.09 for structural steel modifications, signage changes, wayfinding signage, and media center stair stringer work. The amendment raises the total construction contract to $48,163,154.49 without extending the current completion date of October 3, 2026.

Document date · July 17, 2026

Track Jefferson Parish School District contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Jefferson Parish School District.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$73,807.09 (change order); new contract sum $48,163,154.49
Contract type
CONSTRUCTION
Contract term
Original substantial completion 10/03/2026; unchanged by this change order
Renewal date
2026-10-03
Renewal
Change Order 011 adds $73,807.09 to the existing construction contract without changing the contract time, leaving the substantial completion date at October 3, 2026. Substantial completion for the overall project is noted as November 16, 2026, with the new gymnasium substantial completion on April 26, 2027; no further renewal or extension options are stated.
Document type
Contract
Source document
Jefferson Parish Schools Change Order Request 011 2026-07-17

Related contracts

Other contracts from Gibbs Construction Llc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Jefferson Parish School District?

Gibbs Construction Llc was awarded this construction contract by Jefferson Parish School District, as recorded on July 17, 2026. The contract value is $73,807.09 (change order); new contract sum $48,163,154.49.

How much is the Gibbs Construction Llc contract with Jefferson Parish School District worth?

The Gibbs Construction Llc contract with Jefferson Parish School District is valued at $73,807.09 (change order); new contract sum $48,163,154.49, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in Jefferson Parish Schools Change Order Request 011 2026-07-17 (Contract), dated July 17, 2026 from Jefferson Parish School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Gibbs Construction Llc hold?

Gibbs Construction Llc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Gibbs Construction Llc's profile

What is Jefferson Parish School District currently buying?

Explore Jefferson Parish School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Jefferson Parish School District's profile