CONSTRUCTIONAMENDED

T BELL Mechanical Scope Adjusted via Change Orders

Hornell City School District has increased its Phase II Intermediate contract with T BELL by $138,700 through executed and proposed change orders, including additional start-up scope. These changes modify the mechanical and equipment commissioning work.

Document date · June 9, 2026

Track Hornell City School District contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Hornell City School District.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$135,200 written COs to date; $3,500 pending; $138,700 total changes to date
Contract type
CONSTRUCTION
Renewal
Change orders and a proposed start-up change add $138,700 to T BELL’s original contract value for Phase II Intermediate.
Document type
Report
Source document
Hornell City School District Construction Report 2026-06-09

Related contracts

Other contracts from T Bell.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Hornell City School District?

T Bell was awarded this construction contract by Hornell City School District, as recorded on June 9, 2026. The contract value is $135,200 written COs to date; $3,500 pending; $138,700 total changes to date.

How much is the T Bell contract with Hornell City School District worth?

The T Bell contract with Hornell City School District is valued at $135,200 written COs to date; $3,500 pending; $138,700 total changes to date, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a report record.

Where was this contract approved?

This contract appears in Hornell City School District Construction Report 2026-06-09 (Report), dated June 9, 2026 from Hornell City School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does T Bell hold?

T Bell may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View T Bell's profile

What is Hornell City School District currently buying?

Explore Hornell City School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Hornell City School District's profile