CONSTRUCTIONAMENDED

Town of Orchard Park AgendaPacket Town Board Meeting 2026-05-20

Final change order for CAC generator project

Retention amount $8,908.05; Original contract $157,300.00; Total change order amount to date $178,161.00Town of Orchard ParkGREENAUER BLACKTOP INCMay 20, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Town of Orchard Park is processing the final change order and release of $8,908.05 in retained funds to Greenauer Blacktop Inc. for the Community Activity Center Generator Installation Project. The original $157,300.00 contract has been adjusted through change orders to a total of $178,161.00.

Contract Details

Contract Amount

Retention amount $8,908.05; Original contract $157,300.00; Total change order amount to date $178,161.00

Vendor

GREENAUER BLACKTOP INC

Agency

Town of Orchard Park, NY

Contract Type

CONSTRUCTION

Document Date

May 20, 2026

Renewal Info

Final change order with release of retention; contract amount amended from $157,300.00 to $178,161.00 and project is being closed out.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free