South Coast Water District Awards Construction Contract to Insituform Technologies Inc (April 2026)
- Disclosed value
- $572,904 original construction contract; net project cost after change order $537,706
- From agenda
- Approved
- Apr 22, 2026
The 30-second brief
South Coast Water District awarded a $572,904 contract to Insituform Technologies, Inc. for the 2025-2026 Annual Gravity Sewer Lining Project, rehabilitating over 6,100 feet of sewer main via CIPP lining within 60 working days. A subsequent balancing change order reduced the construction cost, bringing total project costs to $537,706.
Insituform Technologies Inc holds this construction contract with South Coast Water District. Its other public contracts on record include work for Parker Water And Sanitation District and City of Lorain.
Term as filed: Construction contract executed August 18, 2025; work commenced November 16, 2025 and completed February 6, 2026 (60 working days).
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $572,904 original construction contract; net project cost after change order $537,706
- Document date
- April 22, 2026
- Term
- Construction contract executed August 18, 2025; work commenced November 16, 2025 and completed February 6, 2026 (60 working days)
- Source document
- South Coast Water District Water/Sewer Advisory Committee Agenda April 2026 (Agenda)
Insituform Technologies Inc's other public contracts
More South Coast Water District contracts
Questions about this contract
Who was awarded the construction contract by South Coast Water District?
Insituform Technologies Inc was awarded this construction contract by South Coast Water District, as recorded on April 22, 2026. The contract value is $572,904 original construction contract; net project cost after change order $537,706.
How much is the Insituform Technologies Inc contract with South Coast Water District worth?
The Insituform Technologies Inc contract with South Coast Water District is valued at $572,904 original construction contract; net project cost after change order $537,706, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agenda record.
Where was this contract approved?
This contract appears in South Coast Water District Water/Sewer Advisory Committee Agenda April 2026 (Agenda), dated April 22, 2026 from South Coast Water District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Insituform Technologies Inc hold?
Insituform Technologies Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is South Coast Water District currently buying?
Explore South Coast Water District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.