CONSTRUCTIONRECOMMENDED

McGann Electric Proposes Field Lighting Electrical Work

McGann Electric proposed a $193,848.99 electrical package for field lighting-related work at North Tapps Middle School, including trenching, conduit installation, and new padmount equipment. The proposal reflects additional work and credits to the original $94,500 contract and is valid for 30 days from June 5, 2025.

Document date · June 12, 2025

Track Dieringer School District contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Dieringer School District.

Get started free

Create a free account · no credit card

Trusted by 200+ enterprise customers and 1,000+ teams on the free plan

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Total Revised Cost: $193,848.99 (Original Contract: $94,500.00; Additional work: $114,948.99; Credits: -$15,600.00)
Contract type
CONSTRUCTION
Contract term
Proposal valid for 30 days from June 5, 2025
Renewal date
2025-07-05
Renewal
Revised proposal cost supersedes the original $94,500 contract amount, incorporating additional scope and credits; price is valid for 30 days from June 5, 2025.
Document type
Contract
Source document
Aries Building Systems Change Order North Tapps Middle School 2025-06-12

Related contracts

Other contracts from Mcgann Electric.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Dieringer School District?

Mcgann Electric was awarded this construction contract by Dieringer School District, as recorded on June 12, 2025. The contract value is Total Revised Cost: $193,848.99 (Original Contract: $94,500.00; Additional work: $114,948.99; Credits: -$15,600.00).

How much is the Mcgann Electric contract with Dieringer School District worth?

The Mcgann Electric contract with Dieringer School District is valued at Total Revised Cost: $193,848.99 (Original Contract: $94,500.00; Additional work: $114,948.99; Credits: -$15,600.00), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a contract record.

Where was this contract approved?

This contract appears in Aries Building Systems Change Order North Tapps Middle School 2025-06-12 (Contract), dated June 12, 2025 from Dieringer School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Mcgann Electric hold?

Mcgann Electric may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Mcgann Electric's profile

What is Dieringer School District currently buying?

Explore Dieringer School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Dieringer School District's profile