Pilarcitos Wellfield Construction Progress by GSW Construction
Coastside Co Water DistrictUtility District · Half Moon Bay, CA- Document date
- Mar 6, 2026
The 30-second brief
GSW Construction continued work onsite for the Pilarcitos Wellfield Replacement Project in March 2026. All wells have been drilled and well development is commencing.
Gsw Construction holds this construction contract with Coastside Co Water District. Its other public contracts on record include work for Oro Loma Sanitary District and Stege Sanitary District.
See every contract and contact at Coastside Co Water District.
See every contractFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Document date
- March 6, 2026
- Vendor
- Gsw Construction
- Source document
- Monthly Operations Report March 2026 (Report)
Gsw Construction's other public contracts
More Coastside Co Water District contracts
Questions about this contract
Who was awarded the construction contract by Coastside Co Water District?
Gsw Construction was awarded this construction contract by Coastside Co Water District, as recorded on March 6, 2026.
What type of contract is this?
This is a Construction contract, documented as a report record.
Where was this contract approved?
This contract appears in Monthly Operations Report March 2026 (Report), dated March 6, 2026 from Coastside Co Water District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What other contracts does Gsw Construction hold?
Gsw Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
Show 1 more question
What is Coastside Co Water District currently buying?
Explore Coastside Co Water District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.