Washoe County Awards Construction Contract to Plenium Builders Inc (February 2026)
- Disclosed value
- Not to exceed $20,325,158.00 plus $5,350,000.00 project allowance
- From minutes
- Approved
- Feb 10, 2026
- Renews
- Free account
The 30-second brief
Commissioners approved a Guaranteed Maximum Price #2 construction agreement with Plenium Builders Inc. for up to $20,325,158.00, plus a $5,350,000.00 project allowance, to renovate the Washoe County Behavioral Health Facility. Work is expected to start in March 2026 with completion targeted for mid-2027.
Plenium Builders Inc holds this construction contract with Washoe County. Its other public contracts on record include work for Truckee Meadows Fire Protection District.
The renewal date is on record. A free account shows it, with the renewals for every Washoe County contract.
Know when this contract comes back up.
See the renewal dateFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- Not to exceed $20,325,158.00 plus $5,350,000.00 project allowance
- Document date
- February 10, 2026
- Term
- Project work anticipated to commence on or about March 2, 2026, with completion targeted by July 2, 2027
- Renews
- Free account
- Vendor
- Plenium Builders Inc
- Agency
- Washoe County
- Source document
- Washoe County Board of Commissioners Minutes February 10 2026 (Minutes)
Plenium Builders Inc's other public contracts
More Washoe County contracts
Questions about this contract
Who was awarded the construction contract by Washoe County?
Plenium Builders Inc was awarded this construction contract by Washoe County, as recorded on February 10, 2026. The contract value is Not to exceed $20,325,158.00 plus $5,350,000.00 project allowance.
How much is the Plenium Builders Inc contract with Washoe County worth?
The Plenium Builders Inc contract with Washoe County is valued at Not to exceed $20,325,158.00 plus $5,350,000.00 project allowance, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a minutes record, structured as a not-to-exceed (ceiling) agreement.
Where was this contract approved?
This contract appears in Washoe County Board of Commissioners Minutes February 10 2026 (Minutes), dated February 10, 2026 from Washoe County. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Plenium Builders Inc hold?
Plenium Builders Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is Washoe County currently buying?
Explore Washoe County's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.