CONSTRUCTIONAMENDED

Building Improvements Contract Time Extended

Stone Harbor Council approved Resolution 2026-S-251, adopting Change Order No. 4 to the contract with R. Maxwell Construction Co., Inc. for the 10206 Third Avenue Building Improvements Project. The no-cost change extends the construction schedule by 321 days to a new completion date of December 16, 2026, with the contract total remaining $1,677,371.84.

Document date · September 1, 2026

Track Borough of Stone Harbor contracts

Get alerts when new contracts are awarded or existing ones approach renewal at Borough of Stone Harbor.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$1,677,371.84
Contract type
CONSTRUCTION
Contract term
Contract time extended by 321 calendar days, new completion date December 16, 2026
Renewal date
2026-12-16
Renewal
Change Order No. 4 is a no-cost, time-extension-only amendment extending the contract by 321 calendar days to December 16, 2026 while keeping the cumulative contract amount at $1,677,371.84.
Document type
AgendaPacket
Source document
Borough of Stone Harbor AgendaPacket Regular Meeting 2026-09-01

Related contracts

Other contracts from R. Maxwell Construction Company Inc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Borough of Stone Harbor?

R. Maxwell Construction Company Inc was awarded this construction contract by Borough of Stone Harbor, as recorded on September 1, 2026. The contract value is $1,677,371.84.

How much is the R. Maxwell Construction Company Inc contract with Borough of Stone Harbor worth?

The R. Maxwell Construction Company Inc contract with Borough of Stone Harbor is valued at $1,677,371.84, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in Borough of Stone Harbor AgendaPacket Regular Meeting 2026-09-01 (AgendaPacket), dated September 1, 2026 from Borough of Stone Harbor. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does R. Maxwell Construction Company Inc hold?

R. Maxwell Construction Company Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View R. Maxwell Construction Company Inc's profile

What is Borough of Stone Harbor currently buying?

Explore Borough of Stone Harbor's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Borough of Stone Harbor's profile