Truckee Donner Public Utility District Regular Board Meeting Agenda April 2026

Ruppert Inc. slated for SCADA Phase 6 contract

$1,387,753, plus a ten percent change order allowance of $138,775, for a total authorization not to exceed $1,526,528Truckee Donner Public Utility DistrictRUPPERT INCApril 1, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

TDPUD plans to award Ruppert Inc. a contract worth up to $1,526,528 for Phase 6 of its SCADA Reliability Improvement Project. The project will enhance control system reliability with a 10% change order allowance built into the authorization.

Contract Details

Contract Amount

$1,387,753, plus a ten percent change order allowance of $138,775, for a total authorization not to exceed $1,526,528

Vendor

RUPPERT INC

Agency

Truckee Donner Public Utility District, CA

Contract Type

CONSTRUCTION

Document Date

April 1, 2026

More from RUPPERT INC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free