Monterey Mechanical Upgrades Contract Amended to $62.3M, Nine Years

SFPUC increased Monterey Mechanical Co.'s contract by $8 million and 638 days, updating the project scope and term to $62.3M and more than nine years for digester gas utilization upgrades.

Document date · November 10, 2025

Track San Francisco Public Utilities Commission contracts

Get alerts when new contracts are awarded or existing ones approach renewal at San Francisco Public Utilities Commission.

Get started free

Create a free account · no credit card

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
Increase by $8,000,000; revised cost limit $62,293,900
Contract type
CONSTRUCTION
Contract term
Increase by 638 days; revised limit up to 3,231 calendar days (~9 years 3 months)
Renewal
Amended for $8M increase and 638 day extension; prior limits $54,293,900, 2,593 days.
Document type
Agenda
Source document
San Francisco Public Utilities Commission Special Meeting Agenda Nov 2025

Related contracts

Other contracts from Monterey Mechanical Co.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by San Francisco Public Utilities Commission?

Monterey Mechanical Co was awarded this construction contract by San Francisco Public Utilities Commission, as recorded on November 10, 2025. The contract value is Increase by $8,000,000; revised cost limit $62,293,900.

How much is the Monterey Mechanical Co contract with San Francisco Public Utilities Commission worth?

The Monterey Mechanical Co contract with San Francisco Public Utilities Commission is valued at Increase by $8,000,000; revised cost limit $62,293,900, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in San Francisco Public Utilities Commission Special Meeting Agenda Nov 2025 (Agenda), dated November 10, 2025 from San Francisco Public Utilities Commission. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Monterey Mechanical Co hold?

Monterey Mechanical Co may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Monterey Mechanical Co's profile

What is San Francisco Public Utilities Commission currently buying?

Explore San Francisco Public Utilities Commission's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View San Francisco Public Utilities Commission's profile