Helms & Sons Advancing Interceptor Sewer Project
- Document date
- Jun 10, 2026
The 30-second brief
Helms & Sons Excavating continues work on the Interceptor Sewer Project on Houpt Drive, progressing at about 100 feet per day, with the contractor notified of scheduling around the July 3 fireworks event. Roadway and sewer testing work will follow project completion.
Helms & Sons Excavating holds this construction contract with Town of Upper. Its other public contracts on record include work for Town of Weston and City of Sylvania.
See every contract and contact at Town of Upper.
See every contractFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Document date
- June 10, 2026
- Vendor
- Helms & Sons Excavating
- Agency
- Town of Upper
- Source document
- Upper Sandusky Service Committee Minutes 2026-06-10 (Minutes)
Helms & Sons Excavating's other public contracts
More Town of Upper contracts
Questions about this contract
Who was awarded the construction contract by Town of Upper?
Helms & Sons Excavating was awarded this construction contract by Town of Upper, as recorded on June 10, 2026.
What type of contract is this?
This is a Construction contract, documented as a minutes record.
Where was this contract approved?
This contract appears in Upper Sandusky Service Committee Minutes 2026-06-10 (Minutes), dated June 10, 2026 from Town of Upper. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What other contracts does Helms & Sons Excavating hold?
Helms & Sons Excavating may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
Show 1 more question
What is Town of Upper currently buying?
Explore Town of Upper's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.