Stacy and Witbeck Contract Cut by $990K via Value Engineering
- Disclosed value
- $208,824,888 original contract; Change Order No. 1 net deduct of $990,000
- From agenda
- Document date
- May 18, 2026
The 30-second brief
Stacy and Witbeck, Inc.’s $208.8 million construction contract for the Glendale-Hyperion Complex of Bridges Phase 2 was amended by Change Order No. 1 to implement a value engineering proposal that reduces the contract by $990,000 while sharing $1.98 million in savings between the City and contractor. The change consolidates concrete pavement bid items, lowers costs, and increases project contingency under the Caltrans-funded bridge program.
Stacy and Witbeck Inc holds this construction contract with City of Los Angeles - LA Sanitation and Environment. Its other public contracts on record include work for City of Bend and Los Angeles Department of Water & Power.
Term as filed: Approximately 1,800 calendar days from Notice to Proceed issued February 17, 2026.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Amount
- $208,824,888 original contract; Change Order No. 1 net deduct of $990,000
- Document date
- May 18, 2026
- Term
- Approximately 1,800 calendar days from Notice to Proceed issued February 17, 2026
- Vendor
- Stacy and Witbeck Inc
- Source document
- Board of Public Works Agenda 2026-05-18 (Agenda)
Stacy and Witbeck Inc's other public contracts
More City of Los Angeles - LA Sanitation and Environment contracts
Questions about this contract
Who was awarded the construction contract by City of Los Angeles - LA Sanitation and Environment?
Stacy and Witbeck Inc was awarded this construction contract by City of Los Angeles - LA Sanitation and Environment, as recorded on May 18, 2026. The contract value is $208,824,888 original contract; Change Order No. 1 net deduct of $990,000.
How much is the Stacy and Witbeck Inc contract with City of Los Angeles - LA Sanitation and Environment worth?
The Stacy and Witbeck Inc contract with City of Los Angeles - LA Sanitation and Environment is valued at $208,824,888 original contract; Change Order No. 1 net deduct of $990,000, covering construction work.
What type of contract is this?
This is a Construction contract, documented as a agenda record.
Where was this contract approved?
This contract appears in Board of Public Works Agenda 2026-05-18 (Agenda), dated May 18, 2026 from City of Los Angeles - LA Sanitation and Environment. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
Show 2 more questions
What other contracts does Stacy and Witbeck Inc hold?
Stacy and Witbeck Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
What is City of Los Angeles - LA Sanitation and Environment currently buying?
Explore City of Los Angeles - LA Sanitation and Environment's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.