Seaver Construction project 65% complete in Norton
Town of NortonCity · MN- Document date
- Mar 25, 2024
The 30-second brief
Seaver Construction is approximately 65% complete for the Senior & Community Center project. The projected timeline is till May 21, 2024, however, schedule does not reflect actual activity completion dates and is not accurate.
Seaver Construction holds this construction contract with Town of Norton. Its other public contracts on record include work for Woburn Housing Authority.
See every contract and contact at Town of Norton.
See every contractFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Document date
- March 25, 2024
- Term
- NA
- Vendor
- Seaver Construction
- Agency
- Town of Norton
- Source document
- town-of-norton-meeting-minutes-2024-03-25_299.pdf (Meeting Minutes)
Seaver Construction's other public contracts
More Town of Norton contracts
Questions about this contract
Who was awarded the construction contract by Town of Norton?
Seaver Construction was awarded this construction contract by Town of Norton, as recorded on March 25, 2024.
What type of contract is this?
This is a Construction contract, documented as a meeting minutes record.
Where was this contract approved?
This contract appears in town-of-norton-meeting-minutes-2024-03-25_299.pdf (Meeting Minutes), dated March 25, 2024 from Town of Norton. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What other contracts does Seaver Construction hold?
Seaver Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
Show 1 more question
What is Town of Norton currently buying?
Explore Town of Norton's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.