ab_won_pat_international_airport_authority_board_m.pdf

Airport Board OKs $1.47M Structural Change Order

$1,465,000.00 (Change Order No. 14); previously negotiated down from $1,565,296.00A.B. Won Pat International Airport Authority, GuamBLACK CONSTRUCTIONSeptember 29, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The GIAA Board approved Change Order No. 14 to the Terminal Building Structural Upgrade and Concourse Isolation Project with Black Construction for $1,465,000.00 to add glazed aluminum curtain walls and required seismic upgrades. The change order was reduced through negotiation from an initial $1,565,296.00 after review by the Designer of Record and Construction Manager.

Contract Details

Contract Amount

$1,465,000.00 (Change Order No. 14); previously negotiated down from $1,565,296.00

Vendor

BLACK CONSTRUCTION

Agency

A.B. Won Pat International Airport Authority, Guam, GU

Contract Type

CONSTRUCTION

Document Date

September 29, 2025

Renewal Info

This is a construction change order increasing the existing contract value; cumulative contract total is not stated.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free