Mason #3 PUD Awards Equipment Contract to Substation Enterprises (September 2024)
- Awarded
- Sep 10, 2024
The 30-second brief
Mason PUD 3 commissioners awarded the bid M3-2024 for the material package for the Belfair switching station to Substation Enterprises. The project is expected to be completed by summer or early fall 2026.
Substation Enterprises holds this equipment contract with Mason #3 PUD. Its other public contracts on record include work for Town of Landis and City of Batavia.
Term as filed: Estimated completion by summer or early fall 2026.
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Equipment
- Document date
- September 10, 2024
- Term
- Estimated completion by summer or early fall 2026
- Vendor
- Substation Enterprises
- Agency
- Mason #3 PUD
- Source document
- Mason PUD 3 Commissioners Meeting Minutes September 2024 (Minutes)
Substation Enterprises's other public contracts
More Mason #3 PUD contracts
Questions about this contract
Who was awarded the equipment contract by Mason #3 PUD?
Substation Enterprises was awarded this equipment contract by Mason #3 PUD, as recorded on September 10, 2024.
What type of contract is this?
This is a Equipment contract, documented as a minutes record.
Where was this contract approved?
This contract appears in Mason PUD 3 Commissioners Meeting Minutes September 2024 (Minutes), dated September 10, 2024 from Mason #3 PUD. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What other contracts does Substation Enterprises hold?
Substation Enterprises may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
Show 1 more question
What is Mason #3 PUD currently buying?
Explore Mason #3 PUD's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.