CONSTRUCTIONAMENDED

Lemon Grove OKs Storm Drain Change Order No. 2

The City of Lemon Grove approved Change Order No. 2 with Montano Pipeline, Inc. for the Edding Drive Storm Drain Improvement Project, adding $20,263.29 for remobilization and restoration work. With this amendment, the construction contract now totals $376,987.46 for replacement and completion of storm drain improvements between Glebe Road and Edding Drive.

Document date · June 16, 2026

Track City of Lemon Grove contracts

Get alerts when new contracts are awarded or existing ones approach renewal at City of Lemon Grove.

Get started free

Create a free account · no credit card

Trusted by 200+ enterprise customers and 1,000+ teams on the free plan

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$20,263.29 (new total $376,987.46)
Contract type
CONSTRUCTION
Renewal
Change Order No. 2 amends Contract No. 2025-08 by adding $20,263.29 for remobilization and completion of 24-inch HDPE storm drain installation and site restoration, bringing cumulative change orders to $58,692.46 and the new total contract amount to $376,987.46.
Document type
StaffReport
Source document
City of Lemon Grove Staff Report Approval of Change Order No. 2 for the Edding Drive Storm Drain Improvement Project 2026-06-16

Related contracts

Other contracts from Montano Pipeline Inc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by City of Lemon Grove?

Montano Pipeline Inc was awarded this construction contract by City of Lemon Grove, as recorded on June 16, 2026. The contract value is $20,263.29 (new total $376,987.46).

How much is the Montano Pipeline Inc contract with City of Lemon Grove worth?

The Montano Pipeline Inc contract with City of Lemon Grove is valued at $20,263.29 (new total $376,987.46), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a staffreport record.

Where was this contract approved?

This contract appears in City of Lemon Grove Staff Report Approval of Change Order No. 2 for the Edding Drive Storm Drain Improvement Project 2026-06-16 (StaffReport), dated June 16, 2026 from City of Lemon Grove. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Montano Pipeline Inc hold?

Montano Pipeline Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Montano Pipeline Inc's profile

What is City of Lemon Grove currently buying?

Explore City of Lemon Grove's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View City of Lemon Grove's profile