Pensacola State College Agenda District Board of Trustees Meeting 2026-06-16

Morette Company Airframe Facility Change Order Deducted & Extended

Deduct ($674,892.90)Pensacola State CollegeMORETTE COMPANYJune 16, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Pensacola State College board approved Change Order #003 with Morette Company for the Airframe & Powerplant Maintenance Training Facility, deducting $674,892.90 and extending the contract by 35 days due to permitting delays.

Contract Details

Contract Amount

Deduct ($674,892.90)

Vendor

MORETTE COMPANY

Agency

Pensacola State College, FL

Contract Type

CONSTRUCTION

Document Date

June 16, 2026

Contract Term

Add 35 days to the contract time due to permitting delays

Renewal Info

Contract amendment extends the completion time by 35 days; amount reduced.