CONSTRUCTIONAMENDED

San Francisco Airport Commission Agenda 2026-06-16

Funding Increase for Terminal 3 West Design-Build Contract

$173,012,162 (new total not to exceed $1,962,804,276)San Francisco International AirportTURNER CONSTRUCTION COMPANYJune 16, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Airport Commission will consider approving Phase C20 to Contract No. 10071.76 with Turner Construction Company to increase funding for Design-Build Services on the Terminal 3 West Modernization Project by $173,012,162, raising the contract’s not-to-exceed amount to $1,962,804,276 with no change in duration. The amendment includes a corresponding adjustment to contingency.

Contract Details

Contract Amount

$173,012,162 (new total not to exceed $1,962,804,276)

Vendor

TURNER CONSTRUCTION COMPANY

Agency

San Francisco International Airport, CA

Contract Type

CONSTRUCTION

Document Date

June 16, 2026

Contract Term

No change to the Contract duration

Renewal Info

Phase C20 amendment increases the contract’s not-to-exceed value and contingency with no change to the existing duration.