Wastewater Plant Change Order #7: Ag Services Construction
Trusted by teams at
Description
The City of Tucumcari will consider Change Order #7 with Ag Services Construction, Inc. for $435,129, upgrading the wastewater plant with SCADA, generators, flow meters, and additional tie-ins, bringing the total project cost to $5,600,072.23 and extending completion to October 18, 2026.
Contract Details
Contract Amount
$435,129 (incremental); New total $5,600,072.23
Vendor
AG SERVICES CONSTRUCTION INC
Agency
City of Tucumcari, NM
Contract Type
CONSTRUCTION
Document Date
June 11, 2026
Contract Term
Original: Various; This amendment adds 104 days. Now through October 18, 2026.
Renewal Date
2026-10-18
Renewal Info
Amendment adds $435,129 and 104 days to contract. Previous change orders totaled $115,770.23. Original substantial completion November 8, 2025; now October 18, 2026.
More from AG SERVICES CONSTRUCTION INC
More from City of Tucumcari
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.