Planned Generator Construction Bid Preparation by EEC
- Document date
- Jan 10, 2023
The 30-second brief
EEC presented plans to prepare Design Build Bid documents for the construction and installation of four generators at the power plant, with the bid process expected to last about two months after initiation.
EEC holds this construction contract with City of Kimball. Its other public contracts on record include work for Town of Hardwick and Town of Winchester.
Term as filed: Approximately two months bid process timeline (future project).
See who signed off on this contract.
See who signed offFree account · 30-second setup · No credit card
Contract details
- Contract type
- Construction
- Document date
- January 10, 2023
- Term
- Approximately two months bid process timeline (future project)
- Vendor
- EEC
- Agency
- City of Kimball
- Source document
- city-of-kimball-meeting-minutes-2023-01-10_963.pdf (Meeting Minutes)
EEC's other public contracts
More City of Kimball contracts
Questions about this contract
Who was awarded the construction contract by City of Kimball?
EEC was awarded this construction contract by City of Kimball, as recorded on January 10, 2023.
What type of contract is this?
This is a Construction contract, documented as a meeting minutes record.
Where was this contract approved?
This contract appears in city-of-kimball-meeting-minutes-2023-01-10_963.pdf (Meeting Minutes), dated January 10, 2023 from City of Kimball. Civic IQ extracts contract records directly from agency meeting documents and solicitations.
What other contracts does EEC hold?
EEC may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.
Show 1 more question
What is City of Kimball currently buying?
Explore City of Kimball's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.