Final Change Order for 63rd Street Improvements
Trusted by teams at
Description
The Board will consider Change Order #3 (Final) with Gunter Construction for the 63rd Street and Zoo Drive Improvement project, increasing the contract by $36,431.49 to a total of $3,435,693.16 and extending completion to June 30, 2026.
Contract Details
Contract Amount
$36,431.49 (change order); total contract $3,435,693.16
Vendor
GUNTER CONSTRUCTION
Agency
Kansas City Aviation Department, MO
Contract Type
CONSTRUCTION
Document Date
May 3, 2026
Contract Term
Extended to June 30, 2026
Renewal Date
2026-06-30
Renewal Info
Change Order #3 is identified as final and increases the contract by $36,431.49, setting the total at $3,435,693.16 and extending the term to June 30, 2026.
More from GUNTER CONSTRUCTION
More from Kansas City Aviation Department
Kansas City Neighborhood Planning and Development Committee AgendaPacket 2026-05-19
Kansas City Neighborhood Planning and Development Committee AgendaPacket 2026-05-19
Kansas City Finance, Governance and Public Safety Committee Agenda Packet 2026-05-19
Kansas City Neighborhood Planning and Development Committee AgendaPacket 2026-05-19
Kansas City Neighborhood Planning and Development Committee AgendaPacket 2026-05-19
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.