Brighton Central School District Monthly Progress Report April 2026

Electrical contract progresses with minor change order

$2,601,000 (original); Change orders $1,190; Current contract $2,602,190Brighton Central School DistrictCONCORD ELECTRICApril 1, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Concord Electric is executing electrical upgrades for Brighton’s Phase 2 project under a contract originally valued at $2,601,000, now $2,602,190 after a light pole removal change order. Work includes boiler room electrical systems and conduit rough-ins at both the high school and French Road.

Contract Details

Contract Amount

$2,601,000 (original); Change orders $1,190; Current contract $2,602,190

Vendor

CONCORD ELECTRIC

Agency

Brighton Central School District, NY

Contract Type

CONSTRUCTION

Document Date

April 1, 2026

Renewal Info

Phase 2 electrical construction contract (Contract 204) has one approved change order (204-001) adding $1,190. Several open issue items may result in further amendments; no renewal or extension language is provided.

More from CONCORD ELECTRIC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free