Brighton Central School District 2023 Capital Improvement Project Phase 2 Monthly Progress Report March 2026

Electrical Contract with Concord Electric Underway

$2,601,000Brighton Central School DistrictCONCORD ELECTRICMarch 31, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Concord Electric is executing electrical work for the Brighton High School boiler room under a $2,601,000 Phase 2 contract, now revised to $2,602,190 after an approved change order for light pole work. The contractor is installing panels, transformers, conduit, and power for mechanical systems.

Contract Details

Contract Amount

$2,601,000

Vendor

CONCORD ELECTRIC

Agency

Brighton Central School District, NY

Contract Type

CONSTRUCTION

Document Date

March 31, 2026

Renewal Info

Original Contract 204 electrical amount $2,601,000; amended by Change Order 204-001 issued March 2, 2026 for $1,190 for disconnection and removal of light poles, raising the current contract to $2,602,190.

More from CONCORD ELECTRIC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free