Brighton Central School District Monthly Progress Report April 2026

Mechanical contract advancing for boiler room upgrades

$1,888,100Brighton Central School DistrictT BELL CONSTRUCTIONApril 1, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

T. Bell Construction is the mechanical contractor for Brighton’s Phase 2 capital project, executing boiler room piping and equipment work under a $1,888,100 Contract 202. As of late April 2026, the contract has no approved change orders and is approximately 36% complete.

Contract Details

Contract Amount

$1,888,100

Vendor

T BELL CONSTRUCTION

Agency

Brighton Central School District, NY

Contract Type

CONSTRUCTION

Document Date

April 1, 2026

Renewal Info

Original Phase 2 mechanical construction contract with no approved change orders as of 4/30/2026; several allowance draws are documented. No renewal provisions stated.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free