CONSTRUCTIONONGOING

Brighton Central School District 2023 Capital Improvement Project Phase 2 Monthly Progress Report March 2026

Electrical Contract with Concord Electric Slightly Amended

$2,602,190Brighton Central School DistrictCONCORD ELECTRICMarch 31, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Concord Electric is performing electrical work under Contract 204 for the 2023 Capital Improvement Project, with the contract value adjusted to $2,602,190 after a $1,190 change order for light pole removal. Current work includes VFD installations, power to cooling towers, and wiring for domestic hot water plant equipment.

Contract Details

Contract Amount

$2,602,190

Vendor

CONCORD ELECTRIC

Agency

Brighton Central School District, NY

Contract Type

CONSTRUCTION

Document Date

March 31, 2026

Contract Term

Phase 2 – Contract 204 Electrical scope, approximately Dec 1, 2025 to Aug 31, 2027

Renewal Info

Change Order 204-001 (Issue 008) was issued and approved in March 2026, adding $1,190 for T&M disconnections and removal of light poles at Brighton High School.

More from CONCORD ELECTRIC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free