CONSTRUCTIONAMENDED

Metropolitan Nashville Airport Authority Agenda 2026-06-17

Change Order Adds $10M To Employee Parking Lot Project

$10,036,192 (Change Order); New total contract amount $50,971,692Metropolitan Nashville Airport AuthorityJONES BROS CONTRACTORS LLCJune 17, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

MNAA approved a $10.0 million change order with Jones Bros. Contractors, LLC to undercut and stabilize the subgrade for the Northeast Employee/Valet Storage Parking Lot project. The contract total for the roughly 40‑acre parking facility now stands at $50.97 million, still significantly under the original project estimate.

Contract Details

Contract Amount

$10,036,192 (Change Order); New total contract amount $50,971,692

Vendor

JONES BROS CONTRACTORS LLC

Agency

Metropolitan Nashville Airport Authority, TN

Contract Type

CONSTRUCTION

Document Date

June 17, 2026

Renewal Info

Change order increases contract value; overall project remains under the originally estimated budget.