Parking Lot Contract Increased for Subgrade Work
Trusted by teams at
Description
MNAA approved Change Order 3 with Jones Bros. Contractors, LLC adding $10.04 million for subgrade undercut and stabilization at the Northeast Employee/Valet Parking Lot, bringing the total contract to $50.97 million through December 2026. The change addresses unforeseen soil conditions at the project site.
Contract Details
Contract Amount
Change Order: $10,036,192; Original Contract: $40,935,500; New Total: $50,971,692
Vendor
JONES BROS CONTRACTORS LLC
Agency
Metropolitan Nashville Airport Authority (MNAA), TN
Contract Type
CONSTRUCTION
Document Date
May 20, 2026
Contract Term
Start: November 2025; End: December 2026
Renewal Date
2026-12-31
Renewal Info
Change Order 3 increases contract value; schedule remains through December 2026.
More from JONES BROS CONTRACTORS LLC
More from Metropolitan Nashville Airport Authority (MNAA)
Metropolitan Nashville Airport Authority AgendaPacket Joint Meeting 2026-05-20
Metropolitan Nashville Airport Authority AgendaPacket Joint Meeting 2026-05-20
Metropolitan Nashville Airport Authority AgendaPacket Joint Meeting 2026-05-20
Metropolitan Nashville Airport Authority AgendaPacket Joint Meeting 2026-05-20
Metropolitan Nashville Airport Authority AgendaPacket Joint Meeting 2026-05-20
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.