Metropolitan Nashville Airport Authority Agenda 2026-06-17

MNAA Sets $130M CGMP3 For CONRAC Enabling Work

Not-to-exceed $130,000,000 (CGMP3 only); prior CGMP1 $78,643,118; CGMP2 $81,029,148Metropolitan Nashville Airport AuthorityMESSER SUNDT JV MSJVJune 17, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The MNAA Board is requested to approve Amendment 2 with Messer Sundt JV to establish Component Guaranteed Maximum Price #3 at a not-to-exceed $130 million for enabling and footprint-clearing activities for the CONRAC and Parking Garage D at BNA. The progressive design-build contract now includes three CGMPs totaling nearly $289.7 million toward New Horizon II landside improvements running through September 2029.

Contract Details

Contract Amount

Not-to-exceed $130,000,000 (CGMP3 only); prior CGMP1 $78,643,118; CGMP2 $81,029,148

Vendor

MESSER SUNDT JV MSJV

Agency

Metropolitan Nashville Airport Authority, TN

Contract Type

CONSTRUCTION

Document Date

June 17, 2026

Contract Term

Anticipated contract start July 2025; 1,506 calendar days; projected completion September 2029

Renewal Date

2029-09-30

Renewal Info

This is CGMP3 of up to six CGMPs under a progressive design-build contract; future CGMPs and a final GMP will be brought separately for approval.