Gadberry Wins Change Order for Pump Station HVAC Controls
Trusted by teams at
Description
TRWD approved a $238,893.92 change order for Gadberry Construction to modify air handler unit controllers at the Richland-Chambers High-Capacity Pump Station. An owner-controlled contingency brings the revised contract to $8.3 million, with completion set for early 2027.
Contract Details
Contract Amount
$238,893.92 (with contingency, revised total $8,305,199.13)
Vendor
GADBERRY CONSTRUCTION
Agency
TARRANT REGIONAL WATER DISTRICT A WCID, TX
Contract Type
CONSTRUCTION
Document Date
March 27, 2026
Contract Term
Project completion anticipated by February 22, 2027
Renewal Date
2027-02-22
Renewal Info
Owner-controlled contingency approved; prior change orders total $37,367.66; substantial completion extended 60 days.
More from GADBERRY CONSTRUCTION
Issuing Agency
Utility District
Fort Worth, TX
More from TARRANT REGIONAL WATER DISTRICT A WCID
Tarrant Regional Water District AgendaPacket 2026-06-16
Tarrant Regional Water District AgendaPacket 2026-06-16
Tarrant Regional Water District AgendaPacket 2026-06-16
Tarrant Regional Water District AgendaPacket 2026-06-16
Tarrant Regional Water District AgendaPacket 2026-06-16
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.