CONSTRUCTIONAMENDED

Tarrant Regional Water District Minutes Meeting 2026-03-27

Gadberry Construction Cooling Improvements Change Order Approved

$238,893.92 change order; owner-controlled contingency $233,852.55; revised total $8,305,199.13Tarrant Regional Water DistrictGADBERRY CONSTRUCTIONMarch 27, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Board approved a $238,893.92 change order with Gadberry Construction for air handler unit controller modifications at the Richland-Chambers High-Capacity Pump Station and added a 3% owner-controlled contingency, bringing the contract total to $8,305,199.13. Funding is from the Bond Fund.

Contract Details

Contract Amount

$238,893.92 change order; owner-controlled contingency $233,852.55; revised total $8,305,199.13

Vendor

GADBERRY CONSTRUCTION

Agency

Tarrant Regional Water District, TX

Contract Type

CONSTRUCTION

Document Date

March 27, 2026

More from GADBERRY CONSTRUCTION

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free