Payment Approved for STP Digester & Bar Screen Project
Trusted by teams at
Description
Palmer Plantation MUD No. 2 approved Progress Estimate No. 13 from R & B Group, Inc. for $28,552.19 for the Removal and Replacement of Digester and Bar Screen at the STP. The revised total contract value is $2,777,668.65 after deductive Change Order No. 1.
Contract Details
Contract Amount
$28,552.19 (this pay request); Total contract $2,777,668.65 after CO 1
Vendor
R & B GROUP INC
Agency
Palmer Plantation Mud 2, TX
Contract Type
CONSTRUCTION
Document Date
February 18, 2026
Contract Term
Original 300 days to substantial completion and 270 days to final completion. No change in time from Change Order No. 1.
Renewal Date
2026-10-28
Renewal Info
Monthly progress payments; contract amended by CO 1; final completion remains unchanged.
More from R & B GROUP INC
More from Palmer Plantation Mud 2
Palmer Plantation Municipal Utility District No. 2 Agenda Notice of Meeting 2026-06-17
Wallace & Philbin, L.L.P. Attorney's Report 2026-05-20
Wallace & Philbin, L.L.P. Attorney's Report 2026-05-20
Wallace & Philbin, L.L.P. Attorney's Report 2026-05-20
Wallace & Philbin, L.L.P. Attorney's Report 2026-05-20
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.