Palmer Plantation MUD No. 2 Engineering Activity Report February 2026

Deductive Change Order Approved for STP Project

($25,915.35) (deduction); new contract total $2,777,668.65Palmer Plantation Mud 2R & B GROUP INCFebruary 18, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Palmer Plantation MUD No. 2 approved Change Order No. 1 with R & B Group, Inc., decreasing the Digester & Fine Screen project contract by $25,915.35, with no adjustment to time.

Contract Details

Contract Amount

($25,915.35) (deduction); new contract total $2,777,668.65

Vendor

R & B GROUP INC

Agency

Palmer Plantation Mud 2, TX

Contract Type

CONSTRUCTION

Document Date

February 18, 2026

Contract Term

Original 300 days substantial, 270 days final completion. No time change from this CO.

Renewal Date

2026-10-28

Renewal Info

First change order; contract total revised down. Does not modify completion date.

More from R & B GROUP INC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free