Palmer Plantation MUD No. 2 Engineering Activity Report April 2026

Final digester project payment to R & B Group approved

$277,766.87 less $31,032.00 in Economic Disincentives (total $246,734.87)Palmer Plantation Mud 2R & B GROUP INCApril 15, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Palmer Plantation MUDs 1, 2, and Fort Bend County MUD 49 are asked to approve Progress Estimate No. 14 and Final to R & B Group, Inc. for $246,734.87 for the Digester Replacement and Mechanical Fine Screen Addition through January 31, 2026. The payment reflects the final construction work completed, including deductions for economic disincentives.

Contract Details

Contract Amount

$277,766.87 less $31,032.00 in Economic Disincentives (total $246,734.87)

Vendor

R & B GROUP INC

Agency

Palmer Plantation Mud 2, TX

Contract Type

CONSTRUCTION

Document Date

April 15, 2026

Contract Term

Through January 31, 2026

Renewal Date

2026-01-31

Renewal Info

Final progress estimate under a construction contract with an original contract amount of $2,808,308.65 and no net change orders to date; this appears to close out the contract.

More from R & B GROUP INC

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free