WWTP Project Change Order Approved for Crosby
Trusted by teams at
Description
The Town of Bristol approved Change Order #7 with Crosby, increasing the contract by $64,923.96 and extending the timeline by 49 days for the wastewater infrastructure project. The new contract total is $24,094,149.81.
Contract Details
Contract Amount
$64,923.96 (change order); new total $24,094,149.81
Vendor
CROSBY
Agency
Town of Bristol, IN
Contract Type
CONSTRUCTION
Document Date
March 19, 2026
Contract Term
49 additional contract days; new substantial completion of Part 1 at 589 days
Renewal Info
Prior six change orders and owner allowance documented; this amendment includes both additional funds and duration. Further amendments possible as project proceeds.
More from CROSBY
More from Town of Bristol
Town of Bristol AgendaPacket Regular Meeting 2026-06-04
Town of Bristol AgendaPacket Regular Meeting 2026-06-04
Town of Bristol AgendaPacket Regular Meeting 2026-06-04
Town of Bristol AgendaPacket Regular Meeting 2026-06-04
Town of Bristol AgendaPacket Regular Meeting 2026-06-04
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.