WWTP Project Expanded for Change Order with Crosby
Trusted by teams at
Description
The Town Council approved Change Order #7 with Crosby, increasing the WWTP project by $64,923.96 and granting 49 additional contract days. The revised contract value now totals $24,094,149.81, with time to substantial completion extended for Part 1.
Contract Details
Contract Amount
$64,923.96 (new total $24,094,149.81)
Vendor
CROSBY
Agency
Town of Bristol, IN
Contract Type
CONSTRUCTION
Document Date
March 19, 2026
Contract Term
increase of 49 additional contract days for Part 1, now 589 days to substantial completion
Renewal Date
2026-12-05
Renewal Info
This is the seventh change order; prior amendments and owner allowances noted in project summary.
More from CROSBY
More from Town of Bristol
Town of Bristol AgendaPacket Regular Meeting 2026-06-04
Town of Bristol AgendaPacket Regular Meeting 2026-06-04
Town of Bristol AgendaPacket Regular Meeting 2026-06-04
Town of Bristol AgendaPacket Regular Meeting 2026-06-04
Town of Bristol AgendaPacket Regular Meeting 2026-06-04
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.