Belle Construction odor control contract extended at vacuum stations
Trusted by teams at
Description
The Key Largo Wastewater Treatment District’s Vacuum Stations Odor Control project is being built by Belle Construction under a $4,009,141.26 construction contract that has been extended by 195 days, moving substantial completion to August 18, 2026. The contractor has installed new odor control tanks, completed final connections, and begun site restoration while awaiting new generator deliveries.
Contract Details
Contract Amount
$4,009,141.26
Vendor
BELLE CONSTRUCTION
Agency
Key Largo Wastewater Treatment District, FL
Contract Type
CONSTRUCTION
Document Date
March 1, 2026
Contract Term
03/28/2025 – 08/18/2026 (525 days) plus 195 days of time extensions
Renewal Date
2026-08-18
Renewal Info
Time extension of 195 days has been granted via change order to allow sufficient time for delivery and installation of new generators; no further renewal terms noted.
More from BELLE CONSTRUCTION
Issuing Agency
Special District
Key Largo, FL
More from Key Largo Wastewater Treatment District
Key Largo Wastewater Treatment District Agenda Item Summary Minutes of May 5, 2026 2026-05-19
Key Largo Wastewater Treatment District Agreement KLWTD Flovac Service Agreement 2026-05-19
Key Largo Wastewater Treatment District Capital Projects Report 2026-05-19
Key Largo Wastewater Treatment District AgendaPacket May 2026 Construction Standards Update 2026-05-19
Key Largo Wastewater Treatment District Agenda Item Summary Minutes of May 5, 2026 2026-05-19
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.