Key Largo Wastewater Treatment District Board of Commissioners Meeting Agenda April 2026

Belle Construction Progresses Vacuum Station Odor Upgrades

$4,009,141.26Key Largo Wastewater Treatment DistrictBELLE CONSTRUCTIONApril 21, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Belle Construction’s $4.01 million Vacuum Stations Odor Control contract is roughly 70% complete, with new odor control tanks operational at all stations and site restoration underway. The project schedule now extends to August 2026 to allow for delivery and installation of new generators.

Contract Details

Contract Amount

$4,009,141.26

Vendor

BELLE CONSTRUCTION

Agency

Key Largo Wastewater Treatment District, FL

Contract Type

CONSTRUCTION

Document Date

April 21, 2026

Contract Term

Start of Contract: 03/28/2025; Substantial Completion Date: 08/18/2026 plus 195 days of time extensions

Renewal Date

2026-08-18

Renewal Info

A time extension of 195 days has been granted via change order to allow sufficient time to receive and install new generators; no additional extensions were taken up at this meeting.

More from BELLE CONSTRUCTION

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free