Major Change Order for Northeast Employee Parking Lot
Trusted by teams at
Description
The Operations Committee is asked to approve Change Order #3 with Jones Bros. for $10,036,192 to address unforeseen excavation and additional shot rock on the Northeast Employee/Valet Storage Parking Lot project. This amendment restores the owner’s contingency and brings the total contract value to $50,971,692 with completion scheduled for November 24, 2026.
Contract Details
Contract Amount
Change Order #3 $10,036,192; Total Contract Amount $50,971,692
Vendor
JONES BROTHERS
Agency
Metropolitan Nashville Airport Authority, TN
Contract Type
CONSTRUCTION
Document Date
May 13, 2026
Contract Term
December 18, 2025 – November 24, 2026 (342 calendar days)
Renewal Date
2026-11-24
Renewal Info
Construction contract executed December 18, 2025 with multiple change orders; Change Order #3 increases scope and restores owner contingency, but no extensions to the contractual completion date are noted.
More from JONES BROTHERS
More from Metropolitan Nashville Airport Authority
Metropolitan Nashville Airport Authority Joint Meeting Agenda Packet May 2026
Metropolitan Nashville Airport Authority Joint Meeting Agenda Packet May 2026
Metropolitan Nashville Airport Authority Joint Meeting Agenda Packet May 2026
Metropolitan Nashville Airport Authority Joint Meeting Agenda Packet May 2026
Metropolitan Nashville Airport Authority Joint Meeting Agenda Packet May 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.