CONSTRUCTIONAMENDED

Metropolitan Nashville Airport Authority Operations Committee Agenda Packet May 2026

Major Change Order for Northeast Employee Parking Lot

Change Order #3 $10,036,192; Total Contract Amount $50,971,692Metropolitan Nashville Airport AuthorityJONES BROTHERSMay 13, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Operations Committee is asked to approve Change Order #3 with Jones Bros. for $10,036,192 to address unforeseen excavation and additional shot rock on the Northeast Employee/Valet Storage Parking Lot project. This amendment restores the owner’s contingency and brings the total contract value to $50,971,692 with completion scheduled for November 24, 2026.

Contract Details

Contract Amount

Change Order #3 $10,036,192; Total Contract Amount $50,971,692

Vendor

JONES BROTHERS

Agency

Metropolitan Nashville Airport Authority, TN

Contract Type

CONSTRUCTION

Document Date

May 13, 2026

Contract Term

December 18, 2025 – November 24, 2026 (342 calendar days)

Renewal Date

2026-11-24

Renewal Info

Construction contract executed December 18, 2025 with multiple change orders; Change Order #3 increases scope and restores owner contingency, but no extensions to the contractual completion date are noted.

More from JONES BROTHERS

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free