Woolwich awards Dunke Street culvert replacement tender
Trusted by teams at
Description
The Township of Woolwich plans to award Tender 2026-03 to Lee Kieswetter Heavy Civil Incorporated for the Dunke Street North culvert replacement at a total cost of $624,385.11 after HST rebate. The construction must commence by August 4, 2026 and be completed within 40 working days, ahead of the ICIP grant funding deadline.
Contract Details
Contract Amount
$624,385.11 after H.S.T. rebate
Vendor
LEE KIESWETTER HEAVY CIVIL INCORPORATED
Agency
Township of Woolwich, Canada
Contract Type
CONSTRUCTION
Document Date
April 28, 2026
Contract Term
Project commencement no later than August 4, 2026 with 40 working days to substantial completion (target completion by September 29, 2026)
Renewal Date
2026-09-29
Renewal Info
One-time construction contract tied to ICIP grant schedule; no renewals discussed.
More from LEE KIESWETTER HEAVY CIVIL INCORPORATED
More from Township of Woolwich
Township of Woolwich StaffReport Tender Award for Cured-In-Place-Pipe (CIPP) Sewer Lining 2026-04-28
Township of Woolwich Staff Report Tender Award for Contract 2026-10 Water Service Valve Replacements on Arthur Street, Elmira 2026-04-28
Township of Woolwich Staff Report Tender Award for Contract 2026-03 Dunke Street North Culvert Replacement 2026-04-28
Township of Woolwich Staff Report Tender Award for Contract 2026-03 Dunke Street North Culvert Replacement 2026-04-28
Township of Woolwich Staff Report Tender Award for Contract 2026-03 Dunke Street North Culvert Replacement 2026-04-28