Dunke Street Culvert Contract to Lee Kieswetter
Trusted by teams at
Description
Township staff recommend awarding Tender 2026-03 for the Dunke Street North culvert replacement to Lee Kieswetter Heavy Civil Incorporated for $624,385.11 after H.S.T. rebate. The construction is scheduled to start by August 4, 2026 and be completed within 40 working days, no later than September 29, 2026.
Contract Details
Contract Amount
$624,385.11 after H.S.T. rebate
Vendor
LEE KIESWETTER HEAVY CIVIL INCORPORATED
Agency
Township of Woolwich, Canada
Contract Type
CONSTRUCTION
Document Date
April 28, 2026
Contract Term
Project commencement no later than August 4, 2026 with 40 working day allowance, completion no later than September 29, 2026
Renewal Date
2026-09-29
More from LEE KIESWETTER HEAVY CIVIL INCORPORATED
More from Township of Woolwich
Township of Woolwich StaffReport Tender Award for Cured-In-Place-Pipe (CIPP) Sewer Lining 2026-04-28
Township of Woolwich Staff Report Tender Award for Contract 2026-10 Water Service Valve Replacements on Arthur Street, Elmira 2026-04-28
Township of Woolwich Staff Report Tender Award for Contract 2026-03 Dunke Street North Culvert Replacement 2026-04-28
Township of Woolwich Staff Report Tender Award for Contract 2026-03 Dunke Street North Culvert Replacement 2026-04-28
Woolwich Township StaffReport Tender Award for the 2026 Paving Program 2026-04-28
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.