Chelmsford Water District Progress Report PFAS Treatment Project March 2026

Waterline Continues Work on Crooked Spring PFAS Treatment Facility

Chelmsford Water DistrictWATERLINEMarch 13, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Chelmsford Water District's PFAS Treatment Project at Crooked Spring is ongoing with Waterline as the contractor. Work includes foundation and utility work, and multiple change orders are under review. Project completion is scheduled for June 28, 2027.

Contract Details

Vendor

WATERLINE

Agency

Chelmsford Water District, MA

Contract Type

CONSTRUCTION

Document Date

March 13, 2026

Contract Term

Estimated completion date of June 28, 2027

Renewal Date

2027-06-28

Renewal Info

No explicit renewal or extension outlined, but official change orders are pending formal signatures and adjustments as needed.