Chelmsford Water District Progress Report PFAS Treatment Project April 2026

Waterline Advances Crooked Spring PFAS Facility Work

Chelmsford Water DistrictWATERLINEApril 13, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Chelmsford Water District continues its construction contract with Waterline for the Crooked Spring PFAS Treatment Facility, now approximately 26% complete and scheduled to finish by June 28, 2027. An approved change order adds $10,931.74 for additional fittings, and an additional cost related to National Grid gas service is anticipated as an owner direct payment.

Contract Details

Vendor

WATERLINE

Agency

Chelmsford Water District, MA

Contract Type

CONSTRUCTION

Document Date

April 13, 2026

Contract Term

Through June 28, 2027 (contract completion date)

Renewal Date

2027-06-28

Renewal Info

Base construction contract for Crooked Spring PFAS Treatment Facility with projected completion date of June 28, 2027; amended via PCO #3 for $10,931.74 with additional no-cost and cost change orders pending.