Waterline Progresses on Crooked Spring PFAS Facility
Trusted by teams at
Description
Chelmsford Water District continues work with Waterline on the Crooked Spring PFAS Treatment Facility, with over 21% of project completion as of March 2026 and ongoing change order processing, including a $10,931.74 approved addition.
Contract Details
Vendor
WATERLINE
Agency
Chelmsford Water District, MA
Contract Type
CONSTRUCTION
Document Date
March 13, 2026
Contract Term
Scheduled completion date June 28, 2027
Renewal Date
2027-06-28
Renewal Info
Four change orders submitted; PCO #3 ($10,931.74) approved pending formal change order signature. Final adjusted contract value to be determined as formal change orders are processed.
More from WATERLINE
More from Chelmsford Water District
Chelmsford Water District Progress Report PFAS Treatment Project April 2026
Chelmsford Water District Progress Report PFAS Treatment Project April 2026
Chelmsford Water District Progress Report PFAS Treatment Project April 2026
Chelmsford Water District Progress Report PFAS Treatment Project April 2026
Chelmsford Water District Progress Report PFAS Treatment Project April 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.