CCWRF Project Change Order Approved for Garney Pacific Inc
Trusted by teams at
Description
The Inland Empire Utilities Agency Board approved a $696,006 compensable time extension change order with Garney Pacific, Inc. for the CCWRF Asset Management and Improvements Project, reflecting SCADA-related design changes and delays. The revised project completion is August 2026, and total project cost remains within budget.
Contract Details
Contract Amount
$696,006
Vendor
GARNEY PACIFIC INC
Agency
Inland Empire Utilities Agency, CA
Contract Type
CONSTRUCTION
Document Date
June 17, 2026
Contract Term
180 calendar day compensable extension plus 128 non-compensable days; revised completion August 2026
Renewal Date
2026-08-31
Renewal Info
This is a negotiated change order amending the original March 15, 2023 contract. Includes a 180-day compensable time extension and 128 non-compensable days, with contract demobilization post-beneficial use.
More from GARNEY PACIFIC INC
More from Inland Empire Utilities Agency
Inland Empire Utilities Agency StaffReport Adopt Resolution No. 2026-6-11, Approving Santa Ana Watershed Project Authority Amended Budget for Fiscal Year 2026/27 2026-06-17
Inland Empire Utilities Agency StaffReport Approve Contract Amendment for Engineering Services During Construction for RP-5 Expansion Project 2026-06-17
Inland Empire Utilities Agency StaffReport Approve Contract Amendments for Sodium Hypochlorite and Polymer Chemicals 2026-06-17
Inland Empire Utilities Agency StaffReport Approve Contract Amendments for Sodium Hypochlorite and Polymer Chemicals 2026-06-17
Inland Empire Utilities Agency StaffReport Fiscal Year 2025/26 Financial Audit Planning and Engagement Communications 2026-06-17
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.