Parsons Engineering Services Contract Amended for RP-5 Project
Trusted by teams at
Description
The Inland Empire Utilities Agency Board is set to approve a $4,757,318 contract amendment with Parsons Water & Infrastructure Inc. for continued engineering services during construction of the RP-5 Expansion Project, extending services through March 2028 and increasing the total authorized contract amount to $45,309,280.
Contract Details
Contract Amount
$4,757,318 (amendment); new total $45,309,280
Vendor
PARSONS WATER & INFRASTRUCTURE INC
Agency
Inland Empire Utilities Agency, CA
Contract Type
PROFESSIONAL_SERVICES
Document Date
June 17, 2026
Contract Term
Additional 28 months (now through March 2028, per construction schedule)
Renewal Date
2028-03-31
Renewal Info
This is a cumulative amendment; prior amendments on March 20, 2024 ($3,113,071), November 16, 2022 ($3,162,474), November 20, 2019 ($12,589,469), August 21, 2019 ($517,494), March 20, 2019 ($495,979), May 17, 2017 ($17,993,681). Services extended by 28 months to March 2028.
More from PARSONS WATER & INFRASTRUCTURE INC
More from Inland Empire Utilities Agency
Inland Empire Utilities Agency StaffReport Adopt Resolution No. 2026-6-11, Approving Santa Ana Watershed Project Authority Amended Budget for Fiscal Year 2026/27 2026-06-17
Inland Empire Utilities Agency StaffReport Approve Construction Contract Change Order for CCWRF Asset Management and Improvements Project 2026-06-17
Inland Empire Utilities Agency StaffReport Approve Contract Amendments for Sodium Hypochlorite and Polymer Chemicals 2026-06-17
Inland Empire Utilities Agency StaffReport Approve Contract Amendments for Sodium Hypochlorite and Polymer Chemicals 2026-06-17
Inland Empire Utilities Agency StaffReport Fiscal Year 2025/26 Financial Audit Planning and Engagement Communications 2026-06-17
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.