CONSTRUCTIONAMENDED

Fire Station 171 construction contract schedule amended

The Sanibel Fire and Rescue District approved a first amendment to its construction contract with Manhattan Construction Company, LLC for Fire Station 171, revising the deadlines to 525 days for Substantial Completion and 555 days for Final Completion from the Notice to Proceed. The amendment aligns the contract with the original Invitation to Bid schedule while leaving all other terms unchanged.

Status
AMENDED
Document date
June 17, 2026
Contract type
CONSTRUCTION
Vendor
Manhattan Construction Company Llc
Agency
Sanibel Fire & Rescue District · FL

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract type
CONSTRUCTION
Contract term
Substantial Completion within 525 days from Notice to Proceed; Final Completion within 555 days from Notice to Proceed
Renewal
First Amendment revises Section 5.2 and 5.3 of the original April 22, 2026 Construction Contract to extend Substantial Completion to 525 days and Final Completion to 555 days from the Notice to Proceed; no changes to price or other terms are indicated.
Document type
Resolution
Source document
Sanibel Fire and Rescue District Resolution Authorizing First Amendment to Fire Station 171 Construction Contract 2026-06-17

Related contracts

Other contracts from Manhattan Construction Company Llc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Sanibel Fire & Rescue District?

Manhattan Construction Company Llc was awarded this construction contract by Sanibel Fire & Rescue District, as recorded on June 17, 2026.

What type of contract is this?

This is a Construction contract, documented as a resolution record.

Where was this contract approved?

This contract appears in Sanibel Fire and Rescue District Resolution Authorizing First Amendment to Fire Station 171 Construction Contract 2026-06-17 (Resolution), dated June 17, 2026 from Sanibel Fire & Rescue District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Manhattan Construction Company Llc hold?

Manhattan Construction Company Llc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Manhattan Construction Company Llc's profile

What is Sanibel Fire & Rescue District currently buying?

Explore Sanibel Fire & Rescue District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Sanibel Fire & Rescue District's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free