Key Largo Wastewater Treatment District Board of Commissioners Meeting Agenda April 2026

Flovac Nears Completion of Collection System Monitoring

$9,689,555.24Key Largo Wastewater Treatment DistrictFLOVACApril 21, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The District reported that Flovac's $9.69 million Collection System Monitoring contract is about 92% complete, with most vacuum pit sensors installed and remaining work focused on grinder pump and force main monitoring. The project remains on schedule toward the extended April 2026 substantial completion date.

Contract Details

Contract Amount

$9,689,555.24

Vendor

FLOVAC

Agency

Key Largo Wastewater Treatment District, FL

Contract Type

TECHNOLOGY

Document Date

April 21, 2026

Contract Term

Start of Contract: 7/26/2022; Substantial Completion Date: 4/22/2026 plus 609 days of time extensions

Renewal Date

2026-04-22

Renewal Info

Current time extensions to the Collection System Monitoring contract total 609 days beyond the original substantial completion date; no additional extensions were acted on at this meeting.