Metropolitan Nashville Airport Authority Operations Committee Agenda Packet May 2026

NES true-up approved for TARI Phase 2 utility work

$868,427.42 (original $702,856.65 plus $165,570.77 true-up)Metropolitan Nashville Airport AuthorityNASHVILLE ELECTRIC SERVICEMay 13, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Operations Committee is requested to authorize payment of a $165,570.77 true‑up invoice to Nashville Electric Service, bringing the total cost of transmission line and transformer relocation for TARI Phase 2 to $868,427.42. The additional charges reflect overtime and extra underground cable required during phased cutovers.

Contract Details

Contract Amount

$868,427.42 (original $702,856.65 plus $165,570.77 true-up)

Vendor

NASHVILLE ELECTRIC SERVICE

Agency

Metropolitan Nashville Airport Authority, TN

Contract Type

UTILITIES

Document Date

May 13, 2026

Renewal Info

Existing relocation agreement executed April 29, 2025 for $702,856.65 now adjusted via true-up to a total of $868,427.42.

More from NASHVILLE ELECTRIC SERVICE

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free