CONSTRUCTIONONGOING

Rhode Island DOT Washington Bridge Snapshot Report September-October 2025

Major design-build construction underway for bridge replacement

$315.55 million Estimated Budget; $339.58 million Notice to Proceed Budget; $14.51 million expenses paid to dateRhode Island Department of TrasportationCONSTRUCTIONNovember 1, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Washington Bridge replacement construction contract, structured as a design‑build with early completion incentives, carries a $339.58 million budget, up from a $315.55 million estimate. RIDOT reports $14.51 million in construction spending to date.

Contract Details

Contract Amount

$315.55 million Estimated Budget; $339.58 million Notice to Proceed Budget; $14.51 million expenses paid to date

Vendor

CONSTRUCTION

Agency

Rhode Island Department of Trasportation, RI

Contract Type

CONSTRUCTION

Document Date

November 1, 2025

More from CONSTRUCTION

Related Contracts

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free